ResLife Renovation Blog

  • The First Glance

    October 10, 2013

    While residents of C-Hall have been busy getting acclimated to the newly renovated south side of the building, our contractors have been hard at work on the north side. Today we are bringing you the first glance of all of the work that has been completed so far on the north side. Much of the […]

  • The Final Countdown

    August 9, 2013

    In just 7 short days, Centennial Hall will re-open and become home to nearly 300 students. Before the final product of these renovations is unveiled next week, we wanted to give you an update of the renovations at this point. The lounges on 3rd, 4th, and 5th floors are almost done. This summer the lounges […]

  • Summer Fun

    July 1, 2013

    Centennial may be quiet in the way of students, but construction is definitely in full swing this summer. Over the course of the summer, Centennial’s main lounge, dining hall, and floor lounges are being renovated. Needless to say, there is not a lack of work to be done in good ol’ Centennial. Since food seems […]

  • Finishing Touches and New Beginnings

    May 29, 2013

    It’s finally here. After a year of waiting, I am very excited to announce that our contractors are putting on the putting a few finishing touches to the south side of Centennial. We have showed you the completed 4th and 5th floors in previous posts, and today we are excited to show you the 2nd […]

  • Details

    April 24, 2013

    There is nothing more exciting than seeing some of the more visible changes happen in a renovations project. Recently, some seriously cool things have been happening on the south side of Centennial. For instance, little pops of color have been showing up all over the place. Each of the five floors in Centennial will have […]

  • Step by Step…

    April 10, 2013

    And day by day, more and more progress is being made on the south side of Centennial. (Did you catch the 90’s pop culture reference?) A few weeks ago on our last post we showed you some of the small details that were beginning to come together. Here are a few updates on more completed […]

  • It’s The Little Things…

    March 20, 2013

    While Centennial has not seemed nearly as noisy lately, plenty of little things have been happening on the South side of Centennial. New lighting fixtures have been put in all of the hallways: The lights will be level with the drop ceiling. All of the door frames have been painted and the walls are ready […]

  • Noise Means Progress

    February 14, 2013

    If it is true that noise means progress and if you have been in Centennial recently, well, then you know that there must be a lot of progress happening. Which there is. Progress is happening throughout the building. One of the noisiest areas in Centennial right now is on the south side of the foyer. […]

  • Elevators, Ramps, and Sprinklers Oh My!

    October 26, 2012

    It has been a very busy, loud, and productive month and a half in Centennial. Our contractors have been working hard and getting quite a bit accomplished. The new elevator in the main foyer has made significant progress. The large hole in the wall is no longer a hole. It is now a cement-brick enclosed […]

  • A Little Bit of Progress

    September 7, 2012

    The last time I posted, C-Hall was one very empty¬†building. But, in the ¬†few short weeks since, the North Side of Centennial is now bustling with students. And with all of those students comes one thing: lots and lots of laundry. But, don’t you fret, Centennial was prepared….with a BRAND NEW LAUNDRY ROOM! This is […]